Bristol Road Train Station

10 January 2014 at 14:11

The Gloucestershire Local Transport Board (GLTB) Prioritised Schemes

GLTB was formed in response to the devolution of funding for local major schemes by the Department for Transport (DfT).

After an initial "call for schemes" exercise, the GLTB has adopted a priority list of schemes, the Train Station on Bristol Road in Stonehouse being one of them.

For further information on the schemes please visit: http://www.gltb.org.uk/index.aspx?articleid=115293

The list contains 14 schemes in total. Based on the existing DfT financial allocation of £9.8 million, it would only currently be possible to fund the top four schemes.  However, more funding may become available in the future.

We would like to know your views on the individual schemes so please submit one complete questionnaire for each scheme you would like to comment on.

If you wish to leave your comments and/or support for the scheme then please visit the following website:

https://gloucestershire-consult.objective.co.uk/portal/trp/travel/majorschemefunding/gltb/gltb_prioriitised

Tags: GLTD | Bristol Road Station | Department for Transport | Stonehouse | Prioritised Schemes | Gloucestershire

Posted in The Environment | Development | Stroud District Council | Stonehouse Town Council | 1 Comments »

UPDATE -Urbaser Balfour Beatty Appeal in respect of Javelin Park

09 January 2014 at 11:30

UP TO DATE INQUIRY NEWS

The Inspector has issued a note to assist Third Parties who wish to speak at the Inquiry. You can read it here.

Please find a list of  the Third Parties who wish to speak at the Inquiry on 14 January here. They are also listed on the latest Programme.

The statements for the session on 14 January can be downloaded here.

Cllr David Drew will be attending to give evidence on behalf of Stonehouse Town Council and the Council remains concerned about the County Council’s lack of consideration to residents views.

The County Council does not appear to be able to quantify the need for the Incinerator but rather follows UBB’s business need for the facility.

Tags: Javelin Park | Incinerator

Posted in Javelin Park Incinerator | The Environment | Development | Stroud District Council | Stonehouse Town Council | Gloucestershire County Council | No Comments

Canal Project Latest - January 2014

06 January 2014 at 15:00

Dudbridge: Work on refurbishing the two locks was completed just in time for Christmas and the towpath was reopened. Unfortunately, flooding on 23rd December seriously damaged the new towpath. This was followed by further flooding on New Year’s Day which caused a collapse of the facing brickwork on the lower lock. The problem is being caused by debris washing down Slad Brook and Painswick Stream, which is blocking the protective grid covering the culvert inlet. Although we have been clearing the grid, it becomes blocked during high flows, when it is too dangerous to work. We are now examining possible solutions to the problem.

Good news was the opening of the upper lock on 7th December by 10 year old Crystal Hulls, of Stroud Canoe Club. She led a flotilla of 15 canoes through the lock. The event was well received and attracted regional TV coverage. On 23rd December, Cotswold Canals Trust volunteers took the workboat Wookey Hole through the lower lock, becoming the first vessel in over 60 years to ascend it. An official opening of both locks is being planned for March, which will coincide with an event at The Lawns.

Griffins Mill Lock: Our volunteer team has now taken the lead in refurbishment of the lock, as the Cotswold Canals Trust was unable to muster sufficient resources. Most major work had already been completed. However, work here has now slowed due to the large amount of water in the canal.

In the pipeline for 2014:

  • Creation of a bypass channel at Wallbridge to carry river water around the Lower Lock. This will permit the lock itself to be restored in the summer.
  • Clearance of the channel at Cheapside. This may involve creating a structure to retain the slope above.
  • Clearance of the channel between Wallbridge and Lodgemore – very much a ‘missing link’
  • Erection of a retaining wall below Bowbridge Veterinary Surgery. This will permit restoration of Bowbridge Lock by volunteers.
  • Beginning of work by volunteers at Ham Mill Lock once Griffins Mill Lock is completed
  • Installation of interpretation panels
  • Planting and landscaping at Capels Mill

 

This leaves:

  • Replacement of Lodgemore Bridge. This is dependent on the compulsory purchase currently underway
  • Replacement of Bowbridge Bridge. This is at the tail end of the restoration length and is dependent on funding being available

Tags: Canal Project | January 2014 | Dudbridge | Griffins Mill Lock | Wallbridge | Cheapside | Cotswold Canals Trust

Posted in The Environment | Stroud District Council | Stonehouse Town Council | Canal Project | No Comments